US 2 Tumwater Canyon reopened to two-way traffic
LEAVENWORTH – As of 5:30 p.m., Tuesday, Feb. 10, US 2 Tumwater Canyon (mileposts 90-99) near Leavenworth has reopened to normal, two-way traffic, more than a month ahead of schedule. This fully restores cross-state access on US 2 between Skykomish and Leavenworth. Additional work will be needed this summer to complete permanent repairs along US 2 including Tumwater Canyon and Stevens Pass, which may require closures.
In the aftermath of December’s historic flooding, the Washington State Department of Transportation has been working around the clock to reopen more than 90 roads across the state. The damage to US 2 was extensive, with multiple closures.
The Tumwater Canyon section has been closed since mid-December due to severe washouts.
Reopening this stretch means that US 2 between Skykomish and Leavenworth is fully reconnected, and all sections of US 2 that closed due to flooding and washouts have now reopened to traffic.
“When a major highway is closed, the impacts to the community, to individuals and to businesses are significant,” Governor Bob Ferguson said. “Our WSDOT crews and contractors have been hard at work, 24 hours a day, reopening roads damaged by our historic flooding. Restoring this critical connection between the east and west sides of our state more than a month ahead of schedule is an achievement. Thank you to everyone whose work made this possible.”
“I’m incredibly proud of how our team and contractor rose to the challenge,” said WSDOT Secretary Julie Meredith, “I appreciate their efforts as well as the patience the affected communities have shown as we’ve worked to fully reopen Highway 2.”
Pipkin Construction was the emergency contractor for this project, working around the clock to reopen the road as soon as possible. Emergency repairs included rebuilding of the slope, restoration of drainage, guardrail installation and paving. Additional work is planned for June 2026, weather dependent, to fully restore and repave the roadway.
WSDOT thanks the public for its patience during the closures and repair work, including use of the Chelan County Chumstick Highway as a detour while the Tumwater Canyon was completed.
Check the WSDOT online real-time travel map for current travel conditions.
Timeline
The work to reopen US 2 has been extensive.
- Wednesday, Dec. 10: WSDOT crews closed the highway between Index and Coles Corner (mileposts 35-85) due to multiple washouts and mudslides.
- Thursday, Dec. 11: The closure was extended to include Tumwater Canyon on the east side (milepost 99) of the pass.
- Friday, Dec. 12: Crews were able to clear the roadway to Skykomish (milepost 50) on the west side.
- Thursday Dec. 18: Emergency repairs began on US 2 over Stevens Pass between mileposts 58 and 70.
- Saturday, Dec. 20: Emergency work to remove debris on US 2 east of Skykomish began.
- Tuesday, Dec. 23: Emergency work to repair washouts on US 2 Tumwater Canyon began.
- Monday, Dec. 29: A pilot car began limited travel on US 2 between milepost 71 to the Stevens Pass Resort at milepost 64.Sunday, Jan. 4: Access to US 2 Stevens Pass reopened east of Skykomish.
- Saturday, Jan. 10: US 2 Stevens Pass reopens to normal traffic without pilot car.
- Tuesday, Feb. 10: US 2 Tumwater Canyon reopened to traffic.
Legal Disclaimer:
EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.